PRJ-METRO-CITY-GRID Execution & Mount
Parañaque City Major Arterials

Metro Parañaque Municipal AI Traffic & Security Grid

Client: Parañaque City Government — Command Center

City-wide physical security modernization comprising 54 multi-sensor 4K cameras with automated License Plate Recognition (LPR), optical fiber rings, and centralized Motorola VMS integration with Emergency Command Center.

Camera Grid
54 Units
Storage Capacity
384 TB RAID-6
Timeline
2026-04-10 → 2026-11-30
Overall Progress
88% Completed

Engineering Phases & Milestone Log

System Architecture & Scope

Leadman Field Log

48 of 54 intersections live. Command center video wall active. Final calibration for nighttime LPR reading underway.

PRJ-MCIA-T2-EXP Planning & Survey
Lapu-Lapu City, Cebu

Mactan-Cebu International Airport (MCIA) T2 Expansion CCTV & Video Wall

Client: GMR-Megawide Cebu Airport Corporation (GMCAC)

45 Axis 4K Panoramic Cameras, Milestone XProtect VMS Server, and 3x3 55-inch Barco Video Wall matrix in Airport Security Operations Center (SOC).

Camera Grid
45 Units
Storage Capacity
192 TB RAID-6
Timeline
2026-09-15 → 2026-12-30
Overall Progress
40% Completed

Engineering Phases & Milestone Log

  1. ○ Phase 1: Engineering Survey & Architectural Shop Drawings 80%
  2. ○ Phase 2: Cable Trays, Conduiting & CAT6A STP Network Runs 0%

System Architecture & Scope

Leadman Field Log

Site survey completed. Submitting technical shop drawings for GMCAC engineering approval.

PRJ-NAIA-T3-APRON Execution & Mount
Terminal 3 Apron Tarmac (Bay 101 to Bay 131), Pasay City, Metro Manila

NAIA Terminal 3 Apron CCTV System (28 Avigilon Cameras, Bay 101 to 131)

Client: Manila International Airport Authority (MIAA) - T3 Operations

Turnkey supply, installation, testing and commissioning of 28 Avigilon cameras (3 PTZ and 25 Bullets) scattered across Apron Bays 101 to 131. Includes 1 Big Enterprise VMS Server, 4 Industrial PoE+ Switches, CAT6 & armored fiber connection to airport backbone, 2 commercial LED TV displays, and 3 Ramp Control Operator Workstations deployed by a 13-person specialized labor crew.

Camera Grid
28 Units
Storage Capacity
128 TB RAID-6
Timeline
2026-07-01 → 2026-10-15
Overall Progress
78% Completed

Engineering Phases & Milestone Log

  1. ✓ Phase 1: MIAA Airside Access Permits, FOD Safety & Bay 101-131 Survey 100%
  2. ✓ Phase 2: Apron Trenching, Conduits, CAT6 & Armored Fiber to Airport Backbone 100%
  3. ✓ Phase 3: High-Mast Camera Rigging (3 PTZ & 25 Bullets from Bay 101 to 131) 100%
  4. ✓ Phase 4: Big Enterprise VMS Server & 4x Industrial PoE+ Switches Setup 100%
  5. ○ Phase 5: Ramp Control Room: 2x LED TV Displays & 3x Operator Workstations 85%
  6. ○ Phase 6: Airside Commissioning, 72-Hour Stress Test & Operator Training 40%

System Architecture & Scope

Leadman Field Log

All 28 Avigilon cameras mounted across Bays 101–131. 1 Big Server and 4 PoE switches configured. Fiber link connected to airport backbone. 13-person crew completing workstation calibration in Ramp Control Room.